Session 68: Other Geosynthetic Applications
Geosynthetic's 87 Conference New Orleans,
USA

PARTOS, A.M. and KAZANIWSKY, P.M.
SITE Engineers, USA
Geoboard Reduces Lateral Earth
Pressures
ABSTRACT
A two level below grade parking garage under a forty story office
building adjacent to a low rise retail plaza is nearing completion in
Philadelphia, Pennsylvania. A subway is located adjacent to the south
property line. The exterior grades at the north are approximately
2.2m (7 ft) higher than those at the south. The difference in
elevations and the potential for a future excavation along the subway
would result in unbalanced lateral earth pressures at the location of
the plaza. It was not feasible to brace the north wall of the garage
below the plaza or employ permanent tiebacks. A design was completed
to reduce lateral at-rest earth pressures against the north basement
wall be mobilizing active lateral earth pressures. Prefabricated,
expanded polystyrene bead drainage geoboards were installed against
the exterior face of the north basement wall. Compacted backfill was
constructed against the 25 cm (10 in) thick drainage geoboards. Load
cells and extensometers were installed to monitor the magnitudes of
lateral earth pressures and deflections of the drainage boards. This
paper presents the design and monitoring system data together with
conclusions regarding the performance of the system.
INTRODUCTION
Figure 1 shows the project site which
occupies a full city block in the business center of Philadelphia,
Pennsylvania. The completed project will consist of a fourth story
west office tower, a future forty story East office tower, and a
centrally located plaza with one and two story retail areas. Two
basement levels will provide parking below the entire site. The
nearly completed West office tower is supported on drilled piers
socketed in mica schist rock. The garage below the West tower and
plaza is completed and supported on drilled piers and spread
footings, respectively.
Figure 2 presents a cross-section through the plaza area. The lowest
garage floor and the Market Street subway platform are approximately
at the same elevation. Market Street grade is 2.2m (7 ft) below JFK
boulevard grade. A temporary retention system consisting of soldier
beams, wooden lagging, and soil tiebacks protected the north west,
and south sides of the approximately 10 m (33ft) deep excavation. A
1.9 m (6 ft) diameter storm sewer was installed along the north wall
of the excavation.
SITE engineers, inc. was retained by the owner to provide
geotechnical engineering services in connection with design and
construction. Figure 3 presents a summary of subsurface conditions
based on borings drilled along the north retaining wall.

PRESENTATION OF PROBLEM
All below grade walls were designed to be non-yielding, braced by
floors, and designed for the at-rest earth pressures computed on the
basis of the existing soil conditions behind the temporary retention
system. The design at-rest earth pressures are shown in Figure 3.
Due to differences in elevations between Market Street and JFK
Boulevard, unbalanced lateral earth pressures exist for the length of
the plaza as shown in Figure 4. The unbalanced design load computed
by the Structural Engineer was on the order of 233 kN/lin m (16
kips/lin ft) of wall.
Further excavation along the Market Street subway for repair or
reconstruction could further increase the unbalanced loading
conditions, but such additional loading was not considered in the
design since maintaining stability would be the responsibility of
others.
The Structural Engineer's review disclosed that modification to the
light plaza steel frame by providing bracing to the lateral loads was
not feasible. Permanent tiebacks anchored under JFK Boulevard could
not be considered due to easement problems beyond the JFK Boulevard
property line. Therefore, it was necessary to search for methods of
reducing the lateral earth pressures against the North wall of the
plaza.

METHODS OF REDUCING LATERAL EARTH PRESSURES
Several schemes were considered as listed
in Table 1. The relevant functions of each method are also
listed.
Table 1: Descriptions of Methods of
Reducing Lateral Earth Pressures
Description of Method
Function
1. Light Weight Cellular - Reduction in density
Concrete BAckfill - Mobilization of high value of
Cohesion
2. Stabilized Backfill - Increase of angle of internal
friction
- Increase of cohesion
3. Elastic Drainage - Inducing quasi-active stress
Board on Face of Wall - conditions by providing yielding
media
After taking into consideration costs, scheduling, etc., the
Construction Manager selected the drainage board scheme.
DRAINAGE BOARD DESCRIPTION AND
PROPERTIES
The basic use for drainage boards is to
provide rapid drainage capability for below grade structures, thus
eliminating build-up of hydrostatic pressures against retaining
walls, foundations, etc. Most drainage boards consist of rigid, thin
"egg
crate"
like sheets molded from polystyrene. One product, the "Geotech Drainage
Board,"
consists of molded blocks of expanded polystyrene beads bonded
together with adhesive compound. It deforms during load application.
Application thicknesses vary from 2.5cm (1 in.) to 60 cm (24 in.).
This product was selected on the basis of the predictability of
stress-strain relationships and the availability of varying
thicknesses.
A 3.8 cm (1.5 in.) thick by approximately 15 cm (6 in.) square
manufacturer's sample was tested by uniaxial loading in an unconfined
condition. The stress-strain relationships are presented in Figure
5.
Testing of two and three samples stacked-up provided results similar
to those of the single sample board. The observed modulus of
elasticity for the drainage board was approximately 220
kN/m2 (2.34
tsf) in the load range of 12 kN/m2 (0.13 tsf) and on the order
of 414 kN/m2
(4.4 tsf) above that load interval. These values are in general
agreement with the stress-strain data provided by the
manufacturer.

BACKFILL SOIL PROPERTIES AND DESIGN OF
DRAINAGE BOARD
The excavated on-site granular materials
were proposed as backfill for use the full height of the retaining
walls. The physical and engineering properties of the on-site
granular soils based on laboratory testing and the anticipated field
properties are presented in Table 2.
Table 2: Design Backfill Soil
Properties
Soil Description: Well graded sand, some gravel, some silt
USC Classification: SW-GW
Maximum Laboratory Dry Density*: 20 kN/m3(121 pcf)
Laboratory Void Ratio (e) at Field Density: 0.36
Angle of Internal Friction: 36°
Cohesion (c): 0
Anticipated Average Field in-Place Dry Density: 19
kN/m3 (121
pcf)
Anticipated Average Field in-Place Moisture Content: 10%
Field Percentage of Maximum Dry Density: 93% to 95%
* (ASTM D698)
A well graded, coarse, very angular crushed aggregate (stone) was
specified around the storm sewer line to approximately Elev. 0.9 m
(Elev 3 ft). The estimated range of internal friction is on the order
of 60°, and the in-place density is approximately 22.8
kN/m3 (140
pcf).
The drainage board thicknesses was then selected on the basis of the
anticipated maximum earth pressure (at-rest condition) as shown in
Figure 3, and compression of the board during translational
displacement. A translational movement equal to approximately 0.3% of
the wall height was estimated to mobilize a quasi-active state
condition. (1)
The key design parameters are presented in Table 3.
Table 3: Design of Drainage
Board:
Maximum Design Wall Pressure: 61 kN/m2 (1200 psf)
Maximum Compression of Board: 2.5 cm (1 in.)
Minimum Thickness of Board: 15.2 cm (6 in.)
Selected Thickness of Board: 25.4 cm (10 in.)
The 25.4 cm board thickness was selected to provide a greater margin
of safety because of the possibility that over-compression and some
damage to the board could occur during backfill operations.
The vertical extent of the board was from approximately Elev. 1.5 m
to Elev. 8 m (Elev 5 ft and Elev. 25 ft).
The recommended method of installation required gluing the 1.2 m by
1.2 m by 0.25 m ( 48 in. by 48 in. by 10 in.) thick panels to the
wall in advance of the backfill operations. Since protection of the
board was crucial, temporary protection (plywood on exterior face)
was also specified, if conditions required.
Backfill specifications required placing fill in 20 cm to 30 cm (8 to
12 in.) thick lifts and compacting with a light duty self propelled
vibratory roller, to achieve 93% to 95% of maximum dry density (ASTM
D698).
INSTRUMENTATION
As part of the quality control during construction, it was critical
to evaluate the behavior of the proposed system in order to assess
the validity of the design. To provide data on actual lateral earth
pressures against the retaining wall and the magnitude of drainage
board compression, instruments were installed in the wall along a
near vertical line as shown in Figure 6. The instrumentation
consisted of the following:
Stress Monitoring
Instruments
Type: Carlson S-25 Soil Stress Meter
Description: Resistance type "interface" stress meter
approximately
28 cm (11 in) in diameter, installed in the retaining
wall behind the drainage board.
Number of instruments: 3
Pressure Range: 0 to 170 kN/m2 (0 to 25 psi)
Accuracy: ± 2% of full scale.

Compression (Deflection) Monitoring
Instruments
Type: Extensometer
Description: Field fabricated steel plate (.6 m x .6 m) (2 ft by 2
ft) in
size, installed on the exterior face of the drainage board.
Plate is provided with a steel rod and a scale which
projects through a sleeve to the inside of the wall.
Movements were read against a wire gauge suspended
between floor and ceiling.
Number of Instruments: 3
Accuracy: ± .25 cm (0.1 in)
BACKFILL CONSTRUCTION AND DATA
ACQUISITION
An addendum to the specifications was issued covering installation of
instrumentation, the drainage board, and the placement and compaction
of backfill. The instrumentation became a part of the quality control
procedures. Backfill construction was completed in two phases. The
initial backfill phase consisted of placement of the crushed stone
layer. The contractor elected to backfill the entire width of
excavation up to approximately Elev. 1.5 m (5 ft) with crushed stone
after the stress meters were installed as shown in Figure 7. The
crushed stone fill extended above the lowest stress meter S-1, which
had not been anticipated. Installation of the drainage board and
backfilling (Phase 2) commenced approximately one month later.
Installation of drainage boards and extensometers was done during
backfilling with increasing fill heights. Backfill was placed in
accordance with the recommended procedures with the exception that
protection of the drainage boards with plywood panels was not
required. Total densities from 20.3 to 20.98 kN/m3 (129 to 133 pcf) were
measured in the field.
Stress and extensometer readings were obtained daily. Fill placement
was completed in approximately two weeks time. Readings were also
obtained for a period of four months after completion of the
backfill.
Figure 8 presents the relationship between stresses and increasing
fill heights at each of the three stress meter locations.
The data from Figure 8 are replotted and presented in Figure 9 to
show the relationships between effective net fill heights above meter
S-2 and S-3 and the correspond lateral pressures.
Figure 10 shows the relationship between fill elevation and the
corresponding compression of the "Geoboard " for each of the
extensometers. The computed field stress-strain relationship and the
laboratory stress-strain data are shown in Figure 11.
Figure 12 shows the actual measured and theoretical at-rest and
active lateral earth pressures for the completed backfill condition.


DISCUSSION
FIGURE 8
As shown in Figure 7 the stress meter S-1 was embedded in the stone
fill. Review of the stress readings with increasing fill heights
(Figure 8), indicates that at the location of meter S-1 a stress on
the order of 3.5 kN/m2 (75 pcf) was observed for a fill height of 0.5 m (1.5 ft).
With increasing fill heights, a linear relationship of stress vs fill
height is indicated by meter S-1. It is observed that at full fill
height stress readings gradually increase from approximately 7.0
kN/m2 (150
psf) to 10.1 kN/m2 (215 psf) during a period of approximately four
months.
Review of the readings for stress meters S-2 and S-3 indicate that
they both follow a relatively parallel path. After completion of the
full fill height, readings at meter S-2 and S-3 indicate stress
values of 20.2 kN/m2 (430 psf) and 16.9 kN/m2 (360 psf), respectively.
During the first week of fill completion the stress readings decrease
by approximately 15%. Over the next month the stresses creep upwards
upward until an equilibrium is established. The stress values
observed at meters S-3 and S-2 at equilibrium are 17.2
kN/m2 (365
psf) and 21.9 kN/m2 (465 psf), respectively. The initial 15% reduction in
stresses is due to the deformation of the board and relaxation of the
soil mass. The increase of stresses after the initial decrease can be
the result of soil readjustment and rain water percolation into the
fill.
FIGURE 9
Figure 9 shows the net fill heights above meters S-2 and S-3 vs the
observed stress readings. Information from meter S-1 is not included
because of the crushed stone backfill behind the meter S-1.
A median curve plotted through the data points does not show a linear
relationship but rather an exponential trend. A probability envelope
of 70% was evaluated and is also shown on Figure 9.
Very small deformations were observed for the
extensometers as shown in Figure 10. Maximum deformations of the
drainage board at full fill heights are 0.25 cm (0.1 in.), 0.50 cm
(0.2 in.), and 1.5 cm (0.6 in.) for extensometers E-3, E-2, E-1,
respectively.
Figure 11 shows the computed strain-stress relationships for the
field observations together with the laboratory data. Essentially
fairly good correlation between field measurements and laboratory
data is observed. Bothe curves appear to be nearly parallel, but
there appears to be an apparent shift between the curves indicating
that, under the same stress, the computed strain for the field
condition is less than the laboratory curve. There may be several
explanations:
- The laboratory curve is based on unconfined conditions.
Field conditions are not unconfined.
Therefore, deformations in a confined condition generally
would be less than those in an unconfined state.
- The accuracy of the field readings is limited to
0.25 cm (0.1 in.). This is well below the accuracy of
laboratory instruments with an accuracy of 0.0025mm
(0.0001 in.).
- The extensometers required some seating load as backfill was
being placed before the gauges were zeroed out. Thus it
could be possible that measured total deformation,
and subsequently the strain, is less than the true value.
FIGURE 12
Curve 1 in Figure 12 shows the at-rest earth pressure against the
wall to the stone layer, based on theoretical relationships and not
considering the influence of soil materials beyond the temporary
retention structure.(5)
Curve 2 presents the theoretical relationship (Coulomb) of an active
earth pressure against a wall due to the sand and gravel and stone
backfills.(5)
Curve 3 presents the actual observed pressures against the wall at
the three meter elevations and interpolation between the points. It
is recognized that the actual pressure distribution may not be
necessarily linear. (4)
Comparing Curves 1, 2, and 3 it is obvious that essentially a
condition of very low lateral pressure against the retaining wall has
been attained by application of a yielding material which in this
case was the Geotech drainage board.
It is acknowledged that the temporary retention structure may not
have permitted full development of the theoretical at-rest pressures;
however, it should be noted that continuous monitoring of the
temporary retention system indicated a steady creeping of the
retention system toward the south direction during backfill
construction. Thus we conclude that lateral pressures against the
temporary retention system were transferred onto the backfill and
subsequently onto the permanent basement wall.
CONCLUSIONS
1. Application of the "Geotech
Drainage Board" against a non-yielding retaining wall mobilized a
quasi-active lateral pressure by allowing translational displacement
of the wall backfill.
2. The instrumentation and monitoring programs discussed in this
paper were done as part of the quality control procedures for this
project and were not done for research purposes. Thus, the accuracy
of the instrumentation, particularly deformation measuring, could be
improved.
3. We are not aware of work by others to reduce lateral earth
pressures against non-yielding retaining structures. We propose that
"Geotech Drainage Board" or similar products could be used for this
purpose, but further field and laboratory testing by manufacturers,
researches, etc., is warranted.
4. We offer to share our experience (good and bad) with those
interested in similar applications.
REFERENCES:
1. Fang, Y.S. and Ishibashi, I., "Static Earth Pressures with Various
Wall Movements," Journal of
Geotechnical Engineering,
ASCE, Vol. 112, No. 3, March 1986, pp. 317-333.
2. Gould, J.P., "Lateral Pressures on Rigid Retaining Walls," (1970)
Specialty Conference:
Lateral Stresses in the Ground and Design of Earth Retaining
Structures, ASCE, NY, NY,
pp.219-270
3. Morgenstern, N.R. and Eisenstein, N. "Methods of Estimating
Lateral Loads and Deformation," 1970 Specialty Conference: Lateral Stresses in the
Ground and Design of Earth Retaining Structures, ASCE, NY, NY, pp51-102.
4. Tschebotarioff, G.P., Foundation, Retaining and Earth
Structures, 2nd Edition
(1973), McGraw-Hill Book Co., NY, NY, pp382-388.
5. Winterkorn, M.F. and Fang, H.Y., Foundation Engineering Handbook, Van Norstrand Reinhold Co., NY, NY, 1975,
pp 197-220.
Acknowledgments:
The authors thank John DiGenova, geotechnical engineer, SITE
engineers, Inc. for his assistance during field work and preparation
of this paper; and Kelly A. Romayko for her dedicated assistance in
the preparation of this manuscript.